In the classical Job-Shop problem there are n jobs that must be processed on m machines. Each job consists of a sequence of different tasks (operations). Each task needs to be processed during an uninterrupted period of time on a given machine.
Given a set J of jobs, a set M of machines and a set T of tasks, we denote by τj the number of tasks for a given job j ∈ J. To each task aij corresponds an ordered pair (mij, pij): the task aij needs to be processed on machine mij ∈ M for a period of pij units of time.
This approach looks for a simple and unoptimized solution (schedule) to the well-known Singer & Pinedo benchmark-set.
config.properties contains the path to the benchmark-set.
#JobShop Properties
#Wed Sep 04 08:10:22 COT 2019
path=benchmark-setpath (either relative or absolute) where the .txt files are stored.
Scheduling and exporting to dot format:
package com.github.guillesup.example;
import com.github.guillesup.interactors.BenchmarkReport;
import com.github.guillesup.interactors.JobShop;
public class Example {
public static void main(String[] args) {
var scheduledBenchmark = JobShop.schedule("b101");
System.out.println(BenchmarkReport.getInstance(scheduledBenchmark).toDot());
// Also you can save it.
BenchmarkReport.getInstance(scheduledBenchmark).saveDotToDisk();
}
}dot format:
strict digraph b101 {
graph [center=1 rankdir=LR ordering=out ratio=auto nodesep=0 ranksep=1]
node [shape=circle height=0.7 fixedsize=true]
9 [ label="3:1" ];
8 [ label="2:1" ];
7 [ label="1:1" ];
6 [ label="1:2" ];
5 [ label="3:2" ];
4 [ label="2:2" ];
3 [ label="2:3" ];
2 [ label="1:3" ];
1 [ label="3:3" ];
0 [ label="Init" ];
-1 [ label="End" ];
subgraph {
0 -> 1 [ label=0 ]
0 -> 4 [ label=0 ]
0 -> 7 [ label=0 ]
}
subgraph {
3 -> -1 [ label=5 ]
6 -> -1 [ label=3 ]
9 -> -1 [ label=5 ]
}
subgraph cluster_0 {
subgraph cluster_1 {
label="Job 1"
7 -> 8 [label=2];
8 -> 9 [label=4];
}
subgraph cluster_2 {
label="Job 2"
4 -> 5 [label=4];
5 -> 6 [label=2];
}
subgraph cluster_3 {
label="Job 3"
1 -> 2 [label=5];
2 -> 3 [label=4];
}
}
/* Critical Path */
{
0 -> 1 -> 2 -> 3 -> -1 [color=red]
}
/* Conjunctive Edges of machine 1 */
{
edge[fontcolor=cornflowerblue color=cornflowerblue style=dashed]
2 -> 6 [label=4];
7 -> 2 [label=2];
}
/* Conjunctive Edges of machine 2 */
{
edge[fontcolor=gold2 color=gold2 style=dashed]
8 -> 3 [label=4];
4 -> 8 [label=4];
}
/* Conjunctive Edges of machine 3 */
{
edge[fontcolor=magenta color=magenta style=dashed]
1 -> 5 [label=5];
5 -> 9 [label=2];
}
}Scheduling and reporting to the console:
package com.github.guillesup.example;
import com.github.guillesup.interactors.BenchmarkReport;
import com.github.guillesup.interactors.JobShop;
public class Example {
public static void main(String[] args) {
var scheduledBenchmark = JobShop.schedule("b101");
System.out.println(BenchmarkReport.getInstance(scheduledBenchmark).getReport());
}
}benchmark report:
------------------------------------
Benchmark
------------------------------------
Id: b101.txt
Jobs: 3
Machines: 3
Tasks: 9
Is acyclic: Yes
------------------------------------
Critical Path
------------------------------------
Weight: 14
Length: 4
Path: [Init, 3:3, 1:3, 2:3, End]
+------------+----------+----------+
| Task (m:j) | End time | Due date |
+------------+----------+----------+
| 3:1 | 13 | 10 |
| 1:2 | 12 | 11 |
| 2:3 | 14 | 16 |
+------------+----------+----------+ b101.dot to PNG