Potential Project Breakdown:

gantt
    title 5 Week Project Plan
    dateFormat  MM-DD-YYYY
    axisFormat  %m/%d

    section Week 1
    Create Wireframes for Each UI          :10-29-2025, 11-05-2025
    Design Database Schema                 :10-29-2025, 11-05-2025
    Define Interface Specifications        :10-29-2025, 11-05-2025

    section Week 2
    Setup Backend Framework		             :11-05-2025, 11-12-2025
    Setup Databases                        :11-05-2025, 11-12-2025
    Create Login Interface                 :11-05-2025, 11-12-2025
    Create Administrator Interface         :11-05-2025, 11-12-2025

    section Week 3
    Quote CRUD Operations                  :11-12-2025, 11-19-2025
    Quote Status (draft -> sanctioned)     :11-12-2025, 11-19-2025
    Connect Database(s) with API(s)        :11-12-2025, 11-19-2025
    Test CRUD operations, etc              :11-12-2025, 11-19-2025

    section Week 4
    Conversion + Commission Logic          :11-19-2025, 11-26-2025
    Commission Logic                       :11-19-2025, 11-26-2025
    Create Sales Associate + Worker UI     :11-19-2025, 11-26-2025
    External Processing System Setup       :11-19-2025, 11-26-2025

    section Week 5
    Final Bug Fixes		                     :11-26-2025, 12-03-2025
    UI Polishing		                       :11-26-2025, 12-03-2025
    Verify Data			                       :11-26-2025, 12-03-2025
    Testing [& Documentation?]	           :11-26-2025, 12-03-2025

    Prepare Presentation & Demo (All)      :milestone, 12-03-2025

Loading