docs/Legacy/JobCosting/JobCostingreport.md

Lines changed: 15 additions & 13 deletions
Original file line numberDiff line numberDiff line change
@@ -47,19 +47,21 @@ Farthest to the right, the Normal Calculation and the Actual Job Costing are com
4747
| 1 | Quoted Price/Invoiced | Offered Price from Quote / Order line. The invoice amount is shown after posting the invoice. |
4848
| 2 | Estimated Sales Price | Calculated price including profit. |
4949
| 3 | Direct Cost: Materials | Material Costs without surcharge. |
50-
| 4 | Direct Cost: Sub Contracting | Outwork/Sub-contracting Costs without surcharge. |
51-
| 5 | Contribution Margin 1 | Result of line No.: 1 - 3 - 4 |
52-
| 6 | Direct Cost: Hours | Sum of direct costs (from Direct Cost setup at Cost Center rates per hour). |
53-
| 7 | Direct Cost Total | Result of line No.: 6 + 3 + 4 |
54-
| 8 | Contribution Margin 2 | Result of line No.: 1 - 3 - 4 - 6 |
55-
| 9 | Total Cost | Line No. 6 + Overhead |
56-
| 10 | Profit | Result of line No.: 1 - 9 |
57-
| 11 | Profit Ratio | |
58-
| 12 | Total Hours | Sum of total hours |
59-
| 13 | Error, Cost Price | Sum internal extra work direct costs |
60-
| 14 | Error, Price | Sum internal extra work sales price (12 + surcharge + profit) |
61-
| 15 | Extra Work, Cost | Sum customer extra work direct costs |
62-
| 16 | Extra Work, Sales Price | Sum customer extra work sales price (15 + surcharge + profit) |
50+
| 4 | Expected Cost: Materials | Order material cost from pending invoice amounts. |
51+
| 5 | Direct Cost: Sub Contracting | Outwork/Sub-contracting Costs without surcharge. |
52+
| 6 | Expected Cost: Sub Contracting | Outwork/Sub-contracting Costs from pending invoice amounts. |
53+
| 7 | Contribution Margin 1 | Result of line No.: 1 - 3 - 4 |
54+
| 8 | Direct Cost: Hours | Sum of direct costs (from Direct Cost setup at Cost Center rates per hour). |
55+
| 9 | Direct Cost Total | Result of line No.: 6 + 3 + 4 |
56+
| 10 | Contribution Margin 2 | Result of line No.: 1 - 3 - 4 - 6 |
57+
| 11 | Total Cost | Line No. 6 + Overhead |
58+
| 12 | Profit | Result of line No.: 1 - 9 |
59+
| 13 | Profit Ratio | Profit in percent |
60+
| 14 | Total Hours | Sum of total hours |
61+
| 15 | Error, Cost Price | Sum internal extra work direct costs |
62+
| 16 | Error, Price | Sum internal extra work sales price (12 + surcharge + profit) |
63+
| 17 | Extra Work, Cost | Sum customer extra work direct costs |
64+
| 18 | Extra Work, Sales Price | Sum customer extra work sales price (15 + surcharge + profit) |