Contributing to cpp-critical-path-validator

Thank you for considering a contribution. This validator is used in court-filed forensic schedule reports. Contributions are welcome and the bar is high.


Quick rules

  1. Every commit must pass the existing tests.

    python tests/test_cp_validator.py
    python tests/test_dcma14.py
    python tests/test_cp_forensic.py

    Or with pytest:

    pip install pytest
    pytest tests/
  2. Run all tests before opening a PR. CI runs the same suite on Ubuntu, macOS, and Windows across Python 3.10, 3.11, and 3.12.

  3. No real client XER files in tests. Every fixture must be built synthetically in memory at test time. We deliberately ship no client data with this repo.


Forensic-correctness rules

The validator is used in court. Sloppy contributions ship as evidence.

No data truncation in user-facing output

The validator returns findings as structured Finding instances inside a ValidationReport. Every list inside evidence (e.g. open-ends list, out-of-sequence list, constraint-driven CP list) must be emitted in full. No [:30], no "top 10", no "+ N more". A judge or opposing expert reading the report has to see every affected activity, not a sample.

There is a regression test in test_cp_validator.py that locks this rule in. New checks must follow the same discipline.

Citation discipline

  • Every reference string in a Finding.reference field must cite a real, verifiable source: a DCMA item number, an AACE Recommended Practice section, a federal regulation, or a court decision. No fabricated case names. No invented section numbers.
  • AACE 29R-03 Windows analysis is correctly labeled MIP 3.3 (not MIP 3.7, which is the additive-prospective TIA). This validator does not run Windows analysis but the constraint surface of cp_validator can confuse the two; double-check before adding citations to that area.

Constraint taxonomy discipline

The four-tier constraint taxonomy (HARD_ABSOLUTE / HARD_DATE / SOFT / PREFERENCE) maps to specific P6 24.12 constraint codes. Any change to the taxonomy must update the recommendation prose to match the new tier semantics. A scheduler removing a Mandatory constraint reads different advice than one removing a Start-On.

Score-weights discipline

The CP Confidence Score weights sum to exactly 1.00. Any change to CHECK_WEIGHTS must preserve this. A drifted-sum CP score is a Daubert vulnerability.


Pull-request checklist

  • All existing tests pass on Python 3.10 / 3.11 / 3.12.
  • New behavior is covered by a synthetic test fixture.
  • No real client data appears in the diff.
  • CHANGELOG describes the change.
  • If you changed CHECK_WEIGHTS, the sum is still 1.00.
  • If you added a citation, it is verifiable in a primary source.

Style

  • 4-space indentation. No tabs.
  • Comments explain why, not what.
  • Pure functions where possible.

Reporting bugs

Open an issue at https://github.com/danafitkowski/cpp-critical-path-validator/issues.

A good bug report includes:

  1. The synthetic XER fixture that reproduces the issue (please redact any client data before sharing).
  2. The expected check rating / score / recommendation.
  3. The observed output.
  4. Python version (python --version).
  5. Operating system.

Forensic-correctness bugs (wrong score, missing finding, fabricated citation, silent truncation) are treated as critical.


License

By contributing, you agree your contribution will be licensed under the MIT license that covers the project.


Code of conduct

Be technically rigorous. Cite primary sources. Verify before asserting. Be courteous in code review.