RACI Matrix

Project: [CLIENT_NAME] Power BI Dashboard

Version: 1.0 Last Updated: [DATE]


Legend

  • R = Responsible (does the work)
  • A = Accountable (final decision maker, only one per row)
  • C = Consulted (provides input before decision)
  • I = Informed (notified after decision/completion)

Team Members

Abbreviation Role Name Hours
PM Project Manager [Name] 80
DE Data Engineer [Name] 80
PBI Power BI Lead [Name] 180
UX UX Designer [Name] 30
QA QA Analyst [Name] 20
BO Business Owner [Name] -
TL Technical Lead (Client) [Name] -

Phase 1: Discovery & Data Engineering

Deliverable PM DE PBI UX QA BO TL
Project kickoff meeting R/A I I I I C C
Project charter R/A C C I I A C
Requirements document R C C I I A C
Requirements sign-off R I I I I A C
Data source inventory I R/A C I I C C
Data profiling report I R/A C I I I C
Data quality assessment I R/A C I I I C
Data model schema (ERD) C R/A C I I I C
ETL/Dataflow design I R/A C I I I C
ETL/Dataflow implementation I R/A C I I I I
Data dictionary C R/A C I I I C

Phase 2: Design & Development

Deliverable PM DE PBI UX QA BO TL
Dashboard wireframes C I C R/A I C I
Visual design standards I I C R/A I C I
Wireframe approval R I C C I A I
Power BI data model I C R/A I I I C
DAX measures - core I C R/A I I I I
DAX measures - documentation I C R/A I I I I
View 1 development I C R/A C I I I
View 2 development I C R/A C I I I
View 3 development I C R/A C I I I
Visual formatting/polish I I R A I C I
Initial dashboard review R I C C I A C
Data refresh configuration I R A I I I C
DE knowledge transfer R R A I I I I

Phase 3: Refinement & Testing

Deliverable PM DE PBI UX QA BO TL
Stakeholder feedback incorporation R I A C I C I
Performance optimization I C R/A I I I C
Row-level security implementation I C R/A I I I C
RLS testing/validation I I C I R I A
Test case development R I C I A C I
Functional testing I I C I R/A I I
Data validation testing I C C I R/A I C
Defect logging I I C I R/A I I
Defect triage R/A I C I C C I
Defect resolution I C R/A I C I I

Phase 4: UAT & Deployment

Deliverable PM DE PBI UX QA BO TL
UAT plan R/A I C I C C I
UAT test cases R I C I A C I
UAT facilitation R I C I A C I
UAT defect resolution I I R/A I C C I
UAT sign-off R I I I I A C
Deployment runbook R/A C C I I I C
Access matrix R/A I C I I C C
Production deployment R/A I C I I I C
User training R/A I C I I C I
User guide R I A C I C I
Project documentation R/A C C I I I I
Lessons learned R/A C C C C C C
Project closeout R/A I I I I A I

Ongoing Activities

Activity PM DE PBI UX QA BO TL
Weekly status reports R/A C C I I I I
Status meetings R/A C C C C C C
Risk management R/A C C I I C C
Change control R/A C C I I A C
Budget tracking R/A I I I I I I
Timeline management R/A C C C C I I
Stakeholder communication R/A I C I I C C
Issue escalation R/A C C I I A C

Approval Matrix

Decision Type Approver(s)
Requirements changes Business Owner
Technical design changes Technical Lead + Power BI Lead
Timeline changes PM + Business Owner
Budget changes Business Owner
Resource changes PM
Go/No-go for deployment Business Owner + Technical Lead

Version History

Version Date Author Changes
1.0 [DATE] [Name] Initial version