Sprint Completed by Thurs. Nov 4th
- Procrastinating
- Update scrum board on waffle.io
- Hold work meetings in addition to scrum meetings
- Communicating through Slack
- Regular scrum meetings
-
Work Completed
- Update homepage.
- Account/profile creatation page
- Creating a more advanced page for adding products
- Top menu
- Search Bar
-
Work Not Completed
- Webpage filtered by category
- Edit page allowing users to input location using a map
- User profile page displaying map of current location
- Filter based on location
- Being able to delete users and posts as a website admin
-
Stories Completed
- As a web user, I appreciate a good UI (lowest priority for Sprint 1, but might get bumped down into Sprint 2 if not implemented in Sprint 1)
-
Time Stats
- 83 Hours
- 14 Days
- 0.5 Stories/Week